The Project at the Entrance of the city - Jerusalem Municipality

The Project at the Entrance of the City

​On Wednesday evening, July 26, 2017, work will begin to add a third traffic lane on "Heichal NaMishpat Street and on HaNasee HaShishi Street

תצוגת תאריך

7/30/2017

12/31/1969 6:00 PM

תמונה1

​Following are the traffic arrangements within the framework of the construction:

  • Heichal HaMIshpat Street will be closed between New York Square and Zvulun Hammer Street.
  • The work will be carried out throughout the day and intermittently throughout the night, in order to minimize disturbance to residents and traffic.
  • Depending on the progress of the work, there may be changes in the traffic arrangements on HaNasi HaShishi Street.

Extensive efforts are being made to prevent the work from disturbing the routine of residents and passers-by, but there may be some inconvenience.
Duration of work: July 2017 to March 2018.
We apologize for the temporary inconvenience and are committed to answering any request.
For additional information, please contact the Lev Ha'Ir Community Center at 02-6214770.

 